Ballantyne are a third generation, family-owned dairy production company based in Melbourne, Victoria. Proudly Australian since 1929, Ballantyne's state-of-the-art facilities allows them to satisfy the needs of consumers and commercial customers.
Project Profile
- Assessment - Many factors were considered by the customer including emissions reduction impact, energy prices and available incentives for the project. Agile Energy assessed all variables and created the business case for board approval.
- Contracting - When the project was approved by the board, they wanted it done in a hurry, giving a deadline of 9 weeks from contract execution (This is a record time to install this system).
- Operate & Install – We designed, engineered, installed and project managed throughout the installation process. Solar panels were delivered from Brisbane to Melbourne the day after contract execution to ensure the project could start on time and we brought a team of 15 to site to commence installation. Installation was seamless despite the tight timeframe. The project was delivered a week early to outstanding quality and 10 out of 10 feedback from the customer.
- Approvals – all approvals were directly managed by us for the grid connection and any local council requirements.
Agile were excellent in all areas of direct responsibility - there was regular clear communication, good site management, very good execution of a large scope on a short timeframe and a consistent approach to engaging constructively with the site during the project. Safety management was generally very good...issues were addressed promptly when they were identified. I would recommend Agile Energy highly.
Alex Heddles - Project Engineer
Pay $0 upfront with Agile Energy's tailored PPA
Agile Energy offers a range of Power Purchase Agreements (PPA) to suit individual business needs. We are also the only providers in the industry who offer a 3-year PPA, allowing our customers to
Learn more about our Power Purchase Agreement.